*
DOCUMENT : 9
Beyond
the Beaten Track
THE MUMBAI
URBAN Transport Project (MUTP) was designed toimprove Mumbai’s
traffic and transportation system. It involves many agencies,including the government
of Maharashtra and the Indian Railways
(a national government agency) who share the cost between them,
the municipal corporation
of Greater Mumbai and the Brihan Mumbai Electric
Supply Undertaking. The project
cost is over Rs 7,000 crores
(around US$ 175 million)
and includes funding from a World Bank loan of Rs
2,300 crores (around US$
57.5 million).
The project
is underway and includes the laying of new railway lines, the extension
of station platforms (to allow longer trains), the removal of
road crossings,
station improvements and the resettlement of households living within 10
metres (30 feet) of the tracks. This should
allow an increase in rail capacity
of up to 35 per cent (through higher train frequency during
peak hours), a
reduction in journey times and improvements in the flow of
passengers and vehicles
in and around selected stations. These measures are also far
cheaper than laying new tracks. However, to achieve this, some
15,000 households
living along the tracks and some 4,000 living around the stations
first had to be moved.
LONG BEFORE
THIS project to improve the railways and resettle people from along the
tracks was developed, the Railway Slum Dwellers Federation
had collected
data about the settlements along the tracks, mapped them, set up women’s
savings and credit groups and supported the formation of housing cooperative
societies. This was not just to collect data but also as a means
of community mobilization.
The Alliance
also managed the resettling of some 900 families in 1999 when the Indian
Railways wanted a piece of land cleared urgently. The families were resettled
to Kanjur Marg in
temporary one-room (120 square foot/11.1
square metre) dwellings with electricity and
communal provision for water and
sanitation, while permanent apartments measuring 225 square feet (20.9
square metres) in multi-storey buildings were
to be constructed. Again, the
resettlement was greatly facilitated by the fact that those who were
moved already had strong well-established community organizations.
IN FEBRUARY/MARCH
2001, the Alliance had to cope with an unexpected
eviction: the Indian
Railways demolished over 2,000 huts along the Harbour railway line
– which was against state government policy and against the stipulations
of the Mumbai Urban Transport Project. The Federation responded by mobilizing
thousands of its members to shut down the city's railway system.
The Railways claimed that they were clearing illegal structures that had
been built after January 1, 1995 – as a state law decrees that no slum dwelling
constructed before this date may be demolished without alternative
land being provided. It took five days before the demolitionscould be halted.
Staff from the National Slum Dwellers Federation and SPARC had
tried to stop the demolitions by being present on site, but
the Indian Railways
simply concentrated on demolitions wherever and whenever Federation
leaders or government officials were absent. The next day, at an emergency
meeting convened by the state chief secretary, the state government
decreed that all demolitions must stop. Land sites were identified to accommodate
the evicted households and the National Slum Dwellers Federation
was given the responsibility for managing the resettlement
and overseeing
the construction of formal housing.
AROUND
60,000 PEOPLE were resettled in just over a year without any
municipal or police
force, although the need for rapid implementation meant that it was
not possible to have permanent accommodation ready for all those
who moved. The 60,000 people who moved now live in secure, better-quality
accommodation with provision for piped water, sanitation and electricity.
As a consequence of the resettlement, more trains are running on
the same tracks and at greater speeds. Travelling
times have been reduced
and the rail system’s performance improved.
|